Husky Energy and CNOOC have commenced first production at Liwan Gas Project in the South China Sea.

by: shardul

Posted in:

Asia/Oceania

Husky Energy, CNOOC Start Production at Liwan Gas Project in the South China Sea

Husky Energy and CNOOC have commenced first production at Liwan Gas Project in the South China Sea.

The project consists of three fields: Liwan 3-1, Liuhua 34-2 and Liuhua 29-1, which share a subsea production system, subsea pipeline transportation and onshore gas processing infrastructure.

The Liwan 3-1 field has started production, with initial natural gas sales expected to be approximately 250 million cubic feet per day (mmcf/day) gross and increasing to approximately 300 mmcf/day in the second half of 2014, Husky said Sunday.

Initial sales of condensates and natural gas liquids from Liwan 3-1 are expected to be approximately 10,000 to 14,000 barrels of oil equivalent per day (boe/day) gross.

The Liuhua 34-2 field will be tied into the Liwan infrastructure in the second half of 2014, subject to final approvals. Production from the Liwan 3-1 field is scheduled to go offline for approximately six to eight weeks to provide for the tie-in of the field.

Following the tie in of Liuhua 34-2, combined gas sales are anticipated to increase to approximately 340 mmcf/day (gross). Natural gas from both fields will be processed at the onshore gas terminal at Gaolan and sold to the mainland China market, with initial gas production covered by fixed-price gas sales agreements.

Total gas sales are expected to rise towards a range of 400 to 500 mmcf/day (gross) with the planned tie-in of the Liuhua 29-1 field in the 2016-2017 timeframe.

Husky holds a 49 percent interest in the Production Sharing Contract (PSC) for the Liwan Gas Project and operates the deepwater infrastructure. Its partner CNOOC Limited holds a 51 percent interest in the PSC and operates the shallow water facilities and onshore gas terminal.

The first stage of the $6.5 billion project connecting the Liwan 3-1 field and work to date to tie in the Liuhua 34-2 field have been completed on budget, Husky said.