• Natural Gas News

    Yolla-6 Well at BassGas Starts Production

    old

Summary

AWE Limited has announced that Yolla-6 development well successfully tied-in to export facilities on the Yolla platform and production from that well has commenced.

by: Shardul

Posted in:

Asia/Oceania

Yolla-6 Well at BassGas Starts Production

AWE Limited has announced that Yolla-6 development well successfully tied-in to export facilities on the Yolla platform and production from that well has commenced. 

The operator of the BassGas project, Origin Energy, is monitoring well performance to achieve optimal co-mingling with production from the existing Yolla-4 well.

The early unstablised production rate from the BassGas facilities has now increased to approx. 57 TJ/day following the addition of the Yolla-6 well.  

AWE Managing Director, Bruce Clement, said that the development drilling phase of the BassGas Mid Life Enhancement project was nearing completion. 

“With Yolla-6 now on production, and well performance in-line with data acquired while drilling the well, we are looking forward to additional production from the Yolla-5 well, due to come online in early August,” he said.   

The BassGas project consists of the Yolla offshore well head platform connected by pipeline to the gas processing facility at Lang Lang, Victoria. The Yolla platform is located in Bass Strait, approx. 140km offshore from Kilcunda, Victoria.   

The BassGas Joint Venture partners in T/L1 are: AWE Limited (via subsidiaries) 35.00%; Origin Energy Resources (Operator) 42.50%; Toyota Tsusho Gas E&P Trefoil 11.25%; Prize Petroleum International 11.25%.